By working through key aspects of the system now, our team will have 4-6 months to implement updates to firmware and software packages to ensure smooth, stable operation when your machine arrives.
Production Ordering and Timing
Once the pilot units are received, our team will be working hard to validate all the hardware components. Once this validation is complete, the first production batch of Array and Element units will be placed on order, moving us from pilot to full production.
This order will be happening in January. Factoring in lead times, assembly, and quality control time we estimate that products will begin shipping to customers in Q2 of 2023.
As we move through production, our software and firmware teams will be focused on debugging based on pilot unit feedback, as well as continuing to work through our roadmap of features in order to prepare for delivery of the production units.
Conclusion
Our focus with all developments here is ensuring that the products that reach your facility perform with the highest quality, repeatability, and reliability.
Our implementation of the pilot program comes from learnings over our tens of thousands of Palette products that have been shipped to date.
Rest assured that our team is working hard to bring you the best experience possible, if you have any questions please do not hesitate to reach out to hello@mosaicmfg.com.